Hendrix-Barnhill relocated over 3,500ft of 10” waterline as part of a bridge replacement project. Using our Vermeer 60x90S3, we completed two directional drills, the first being a 1,500ft shot of 12” HDPE under the Neuse River, and the second being a 1,100ft shot of 10” PVC beside the Neuse River overflow bridge. Hendrix-Barnhill had to complete the waterline in two separate sections, with over 700ft of open cut pipe, with two separate tie-ins to make, and completed it within schedule. Hendrix-Barnhill was hired as a subcontractor to Sanford Contractors LLC.